Auxiliary Gymnasium Construction Update - November

Windows and exterior doors have been installed and remaining work starts to focus more so within the inside of the building. The interior walls have been painted including the completion of the Cranbury Vikings logo. The scoreboard has been installed. Permanent light fixtures are in place. Contractors are still waiting on one part to start up the rooftop HVAC units. Once the system is started and runs for a few days, the gymnasium floor can start to be installed. The flooring material is currently being stored on site.  Additional photos can be found here.

 